CONSTRUCTION TIMELINE
Milestone event: Visarjan Vidhi
MARCH 2025
Demolition
APRIL 2025
Soil Inspection
MAY 2025
Milestone event: Bhoomi pooja
JUNE 2025
1.Excavation & Piling
2.Ground Floor Slab
3.Steel Frame
4.Roof Slab
5.External Walls, Windows & Doors
6.Roof Insulation & Waterproofing
7.Ground Floor Finishes
8.Internal Walls + 1st Fix Electrics & Plumbing
9.Ceiling, Drylining, 2nd Fix Plumbing & Electrical
10.Painting & Decorating
11.Temporary Kitchen (from existing appliances)
1.First Floor Slab
2.External Walls, Windows & Doors
3.Roof Insulation & Waterproofing
4.First Floor Finishes
5.Internal Walls + 1st Fix Electrics & Plumbing
6.Ceiling, Drylining, 2nd Fix Plumbing & Electrical
7.Painting & Decorating
8.Temporary Kitchen (from existing appliances)
1.RAFT Slab
2.Concrete Walls
3.Waterproofing
4.Drainage
1.Concrete Block Paviours (Parking)
2.External Decorative Entrance
3.Hard and Soft Landscaping
1.Import and Installation
2.Shikhara (Spire)
3.Dome
4.Windows and other carvings Surrounding the building